8.1 Capital Reimbursement and Tap-In Fees

A sewer connection can carry a large one-time capital charge

Application

During feasibility, obtain the actual current connection/capacity fee schedule and calculate the project’s one-time charge before committing to the site.

Connection capacity can be a major capital cost before the first gallon is processed

A sewer authority may charge a capacity, connection, capital reimbursement, impact, or tap-in fee to recover a new user’s share of collection and treatment infrastructure. The fee can be based on equivalent dwelling units (EDUs), gallons per day of allocated capacity, meter size, or another local method.

Because a septage facility can request tens of thousands of gallons per day of discharge capacity, the connection fee can reach hundreds of thousands or millions of dollars. This cost belongs in feasibility screening—not as a late construction surprise.

Capacity-fee exampleRequired EDUs = Design gallons/day ÷ gallons/day per EDUConnection fee = Required EDUs × fee per EDU
Example

If the ordinance defines one EDU as 228 gpd and the proposed allocation is 20,000 gpd, the project needs about 88 EDUs. At $3,500 per EDU, the connection charge is roughly $308,000 before process equipment or construction. Local formulas vary; use the actual authority schedule.

Design and operating review

  • Request a written fee calculation from the sewer authority.
  • Confirm whether capacity fees are refundable, transferable, or expandable.
  • Separate one-time capacity charge from recurring sewer user charges.
  • Determine whether the allocation limits peak/day or average flow.
  • Include future expansion capacity in the site plan without overbuying unnecessarily.
  • Model financing cost of the fee as part of capital recovery.
Failure mode to avoid

Failure mode: the process equipment is affordable, but the project never budgeted the sewer capacity charge. The connection fee becomes the largest single pre-construction cost and destroys financing.

Technical video segment

Use this focused clip to reinforce the process described above.

Embedded Technical Video

Capital Reimbursement and Tap-In Fees

Segment 40:28–43:40. The written course contains all required learning content.